Belt Conveyor roller Installation

The installation of the belt conveyor is generally carried out in the following stages:
1. Install the belt conveyor frame is from the head frame, and then install the middle of the middle frame, and finally installed tailstock.Before installing the rack, first pull the centerline on the full length of the conveyor,Because the centerline of the conveyor is an important condition for the normal operation of the conveyor belt, it is necessary to align the center line,At the same time also have to frame leveling, the rack on the center line of the allowable error, per meter long ± 0.1mm.But the total length of the conveyor on the rack center of the error shall not exceed 35mm. When all the blocks are installed and identified, the blocks can be connected.
2. Install the drive. When installing the drive, it is important to note that the drive shaft of the belt conveyor is perpendicular to the centerline of the belt conveyor so that the center of the width of the drive roller coincides with the centerline of the conveyor and that the axis of the gear unit is parallel to the drive shaft.At the same time, all shafts and rollers should be leveled. The horizontal error of the shaft, according to the width of the conveyor, allows the range of 0.5-1.5mm. In the installation of the drive device at the same time, you can install the tail wheel and other tensioning device, tensioning device drum axis, and the belt conveyor should be perpendicular to the center line.
3. Install the roller. After the rack, transmission and tensioning device is installed, the upper and lower idler rollers can be installed so that the conveyor belt has a slowly curved arc, and the carriage spacing of the bending section is 1 / 2 ~ 1/3.After the roller is installed, it should be flexible and light.
4. Final confirmation of belt conveyor. To ensure that the conveyor belt is always running on the centerline of the idler and drum, the following requirements must be met when installing the rollers, racks and rollers:
(1) All rollers must be aligned, parallel to each other, and maintained horizontally.
(2) all the rollers in rows, parallel to each other.
(3) The support frame must be linear and maintain horizontal. For this reason, after the drive roller and idler stand is installed, the centerline and the level of the conveyor should be finalized.
5. Then secure the rack on the foundation or floor. After the belt conveyor is fixed, the feeding and discharging device can be installed.
6. When the conveyor belt is attached, the conveyor belt is spread on the roller of the no-load section, and after the drive roller is circled, it is applied to the idler roller.Hanging with a 0.5-1.5t hand winches can be used. When the tension band is connected, the drum of the tensioning device should be moved to the limit position, and the trolley and the spiral tensioning device should be moved to the direction of the transmission.And the vertical pick up device to move the drum to the top. Before tightening the conveyor belt, should be installed reducer and motor, tilting conveyor to install the brake device.
7.After the belt conveyor is installed, it is necessary to carry out the idle test machine.In the idle test machine, pay attention to the operation of the conveyor belt deviation, the drive part of the operating temperature, the operation of the roller, the cleaning device and the guide plate and the conveyor belt surface contact degree, Make the necessary adjustments,At the same time to make the necessary adjustments, the parts are normal before they can carry the load test machine.If the use of screw-type tensioning device, in the load with the test machine running, but also to its tightness and then an adjustment.
Before the belt conveyor is running, first of all to confirm the belt conveyor equipment, personnel, the goods are in a safe and intact state;Second, check the normal parts of the movement without foreign matter, check all electrical lines are normal, normal belt conveyor can be put into operation. And finally to check the supply voltage and equipment rated voltage difference of not more than ± 5%.